Sunday update

Hello guys we are getting to the end of Serpro getting wet and damaged material out of units. We are on the 4th floor now should finish 3,2 and 1 tomorrow.
We will be keeping the fans and dehumidifiers in the halls cause there in no common hall ac that works.

We are working with the general contractor next week to get some scope of work and hope some updates.
Vita Padalion will be helping me update each of you by email we plan on this to start next week so we can give y’all weekly updates on a personal level
I will still post on the bella luna website a short post each day.
Thank you all for you patience and trust in us and we are doing all we can to help protect and get your property back for you all to come and enjoy.

If my updates has misspelled words or not complete sentences sorry I’m workinG 12-14 goes on little sleep I don’t Know what way I’m coming or going sometime.
Not complaining just explaining
Thanks for all the help we have had by owners and all of the supplies that were brought or delivered.
Thanks